Kitchen budget planner

Plan a kitchen renovation budget as a transparent range. Every unit figure below is an editable illustration — replace it with real proposals as they arrive. Nothing you type is stored or sent anywhere.

Illustrative planning range built from editable hypothetical unit assumptions — not a quote, not a bid, not market survey data. Replace every assumption with real proposals before making financial decisions.

1. Room & scope
2. Cabinetry & quantities

Measure along the walls where cabinets run.

10–15% is a common planning allowance for older homes.

Set to 0 if design is already handled.

Defaults to 0 — confirm the current rate for your jurisdiction.

Defaults to 0 — check the agency fee schedule.

3. Unit assumptions

Every seeded figure is an editable illustration, not market data. Open the list and replace anything you have a real proposal for.

Your planning range

Room area: 168 sq ft · High-end custom · Full remodel (same footprint)

Itemized planning range for the kitchen
ItemLowHighAssumption
Demolition & preparation$1,714$2,722Scaled by room area and scope intensity.
Labor & general conditions$22,848$36,288Crew labor, supervision and site protection; scales with area and scope.
Cabinetry & millwork$29,376$46,656Per linear foot; finish band drives the spread.
Countertops$7,181$11,405Assumed to run the cabinet length; edit the unit for stone tier.
Appliances allowance$24,480$38,880Lump-sum allowance — replace with a real appliance schedule.
Sink, faucet & fittings$1,768$2,808Typical kitchen sink + faucet set; edit count via the unit.
Tile & wall surfaces$15,422$24,494Assumes ~1.5× floor area of tiled surface (backsplash/shower walls); edit freely.
Flooring$6,397$10,161Installed per sq ft of floor area.
Electrical & lighting$2,570$4,082Circuits, lighting and controls; scope intensity drives the spread.
Rough & finish plumbing$4,760$7,560Per fixture; layout changes add a separate relocation row.
Construction subtotal$116,516$185,056Sum of the itemized rows above.
Contingency (12%)$13,982$22,207On construction only.
Design allowance (8%)$9,321$14,804On construction only.
Materials tax allowance (0%)$0$0On material rows only; confirm current rates.
Permit/fee allowance$0$0Your editable allowance; check the agency schedule.
Planning range total$139,819$222,067A planning range — not a quote or bid.

What this range excludes

  • Permit and plan-check fees (enter your own allowance after checking the agency fee schedule)
  • Sales tax on materials (editable allowance; confirm the current rate for your jurisdiction)
  • Hazardous-materials survey or abatement (asbestos, lead) in pre-1980 homes
  • Hidden-condition repairs discovered at demolition (rot, galvanized piping, knob-and-tube wiring)
  • Temporary housing, storage or moving costs during construction
  • Landscaping, exterior work or utility service upgrades
  • Design professional fees beyond the optional editable allowance

Preconstruction checklist

  • Measure the room and photograph every wall, the panel and the shut-offs
  • Decide whether the layout stays or moves — relocation drives plumbing and electrical scope
  • Collect two or three cabinet proposals on the same linear-foot basis before comparing
  • Build an appliance schedule with model numbers so allowances are real
  • Ask each bidder what their number excludes — compare exclusions, not just totals
  • Confirm with the City of Santa Barbara whether your scope needs a building permit
  • Hold a contingency of at least 10–15% for hidden conditions in older homes