Beverly Hills planning and approval guide.

A practical sequence for identifying the rules, studies and decisions that may shape a residential project. This is general planning information, not legal advice or a determination of buildability.

1. Confirm jurisdiction and property records

An address inside incorporated Beverly Hills is generally reviewed by the City of Beverly Hills. Confirm the parcel, zoning, recorded improvements and reviewing department before relying on a concept.

  • Verify the exact address and assessor parcel record.
  • Compare existing conditions with available permit records.
  • Identify title, easement or private agreement questions for qualified review.

2. Test planning requirements

Planning feasibility begins with the applicable zone and any overlays. Setbacks, height, lot coverage, access, parking and design review depend on the property and proposed use.

  • Hillside lots can add grading, drainage, access and geotechnical questions to early feasibility.
  • Objective standards and design review should be identified before exterior form and materials are finalized.
  • High-value residential work benefits from disciplined scope definition and coordination across design, engineering and construction.
  • Context flags to verify: hillside and grading, design review, luxury.

3. Assemble the review package

The required package follows the scope and site. A coordinated submittal may involve architectural drawings, survey information, structural work, energy documentation and specialist reports.

  • Existing and proposed site information.
  • Architectural plans and project description.
  • Engineering, energy and specialty studies when applicable.

4. Navigate review and corrections

The City of Beverly Hills determines its intake and review sequence. Departments may request corrections or outside-agency clearances before permit issuance. No schedule should be assumed before the city confirms the path.

  • Complete early due diligence and consultant coordination.
  • Submit to the correct planning and building channels.
  • Track comments, coordinated responses, clearances and issuance.

ADU · First submission

Before filing in Beverly Hills

State baseline: confirm the ADU path under current state law. The municipal steps below do not decide parcel eligibility. State ADU rules

First agency
Community Development Planning is the first contact; Building & Safety reviews the building permit.
Bring
Parcel boundary and owner records, existing plans, site survey and intended ADU type; for preapproved plans, show setbacks, easements, utilities, sewer, drainage and emergency access.
First action
Ask Planning which city ADU development guide applies; use the Property Owner Submittal Checklist for a preapproved design.
Municipal implementation
The city separates its preapproved-plan program from site suitability and publishes development guides by parcel context.
Parcel checks still open
Hillside, Trousdale, historic, fire and utility review cannot be assigned from a mailing address or a catalog design.
Next decision
Confirm city limits and guide category with Planning before paying for or adapting a preapproved plan.

Official documents · links checked Sep 26, 2026

Compare first steps across cities →

Project preparation · City of Beverly Hills

What to settle before you file

A printable checklist for one jurisdiction. Nothing here is submitted to us, nothing is stored, and no sign-in is needed — tick what you have, print it, and take the rest to the counter.

Who this applies to

Parcels inside the Beverly Hills city limits. A Beverly Hills mailing address is not the test — Beverly Hills Post Office addresses in the hills above the city are City of Los Angeles territory and follow the Los Angeles rules instead.

Confirm this is your jurisdiction

Confirm the parcel is inside the city limits before reading any Beverly Hills standard. The city's Accessory Dwelling Units page is the entry point for its own forms and development guides.

Beverly Hills — Accessory Dwelling Units

Who reviews what

Local rule, and when it took effect

  • Beverly Hills Municipal Code, Title 10, Chapter 3, Article 50 (accessory dwelling units)

    Ordinance No. 24-O-2903 · Adopted November 19, 2024 · Effective December 20, 2024

    Beverly Hills Municipal Code (Municode)

Not settled yet

  • The Planning Commission reviewed a further amendment to Article 50 on 11 June 2026, addressing SB 543 and AB 1154. Treat it as proposed, not adopted: read the current code text and ask the Planning Division what is in force on the day you file.

    Beverly Hills — Accessory Dwelling Units

The statewide clock

Government Code § 66317 requires a written completeness determination within 15 business days. For a completed ADU application on a lot with an existing dwelling, the agency then has 60 days to approve or deny. A concurrent new primary dwelling may delay that decision, and applicant-requested delay tolls the period. These are decision rules, not an all-in permit guarantee.

Gov. Code § 66317 (California Legislative Information)
Scope decisions that add review
  • A new driveway, changed parking layout or work near the public way must be shown on the site plan. Decide early whether access or frontage work belongs in the application.

  • The residential submittal requirements call for additional records in hillside and Trousdale areas. A topographic survey, grading conditions, retaining work and emergency access may need to be resolved before the site plan is complete.

  • Work that touches a designated or potentially eligible structure adds a review step. Ask the city whether the address carries any historic status before drawing.

  • Under the city's ADU rules the unit cannot be sold separately from the main house, and rentals are limited to terms of 31 days or longer. If the plan was a short-term rental, the plan needs to change.

Documents to gather
  • Beverly Hills asks ADU applicants to complete an affordability questionnaire. Download the current version from the city's ADU page rather than reusing an old copy.

  • Collect prior permits and the approved floor area for the main dwelling so the submitted existing-condition drawings can be reconciled with city records.

  • The city's checklists call for property lines, setbacks, easements, structures, parking, utilities, sewer, drainage and fire access. Residential requirements may also call for a topographic survey and recent title report.

Site conditions still unresolved
  • Panel size and the utility's answer on a service upgrade are not known from the drawings. Ask for it in writing.

  • Where the lateral runs and whether gravity drainage works for a rear unit; a pump changes cost and maintenance.

  • Mature trees near the building footprint can move the unit. Confirm protection status before the footprint is fixed.

Practical next steps
  • Open the municipal code and the city's ADU page on the same day, and note which version you read.

  • Is the parcel inside the city limits, and does the address carry historic or hillside status? Both answers change the scope.

  • The city publishes an ADU development guide and a preapproved plan option; a preapproved plan still needs a site-specific plan set.

Sources read · Sources last read September 24, 2026

Orientation for one parcel, not a determination. Rules change, and only the agency named above can tell you what applies to your address on the day you file. Nothing here promises that a permit will be approved.

Planning questions

Decisions before filing in Beverly Hills

  1. What happens after a submission to Beverly Hills planning?
    The package is typically routed for completeness review, then technical review, corrections and any outside clearances. Track every comment against the coordinated drawing set, and confirm the current process and turnaround with the city rather than assuming a timeline.
  2. How does a sloped lot change a project here? (Beverly Hills)
    On a slope, the foundation approach, retaining walls, driveway gradient, drainage path and construction access are a single connected decision. The practical first step is confirming slope percentage, mapped geologic conditions and the local grading permit threshold for the specific parcel.
  3. Who reviews the exterior design? (Beverly Hills)
    Either staff applying objective standards or an appointed review body, depending on the scope. Identify which applies, its meeting cadence and its submittal package early, because it affects both the drawing scope and the schedule.
  4. What usually goes wrong on a high-value build? (Beverly Hills)
    Coordination, not design. Long lead items, custom fabrication and unresolved engineering are the usual causes of delay, so a written scope with documented assumptions and confirmed lead times matters more than an early price.

Initial review

Turn the guide into next steps.

Share the address and intended scope to organize a property-specific review.

§ VI · Begin a project

Plan your project in Beverly Hills.

Share the property context and project goals for an initial review.

RecipientProject planning
Project cityBeverly Hills