Schedule questions · 448 answers · 2688 total in the reference desk
Timeline & Phases
What influences sequencing from early study through closeout.
Four separate things decide the timeline
State baseline reviewed September 26, 2026. Local procedures, exceptions and parcel conditions still apply.
The statutory review clock
After an ADU application is submitted, the local agency must say in writing within 15 business days whether it is complete, and generally approve or deny a complete application within 60 days (Gov. Code § 66317). The clock measures agency review of a complete application — not design, corrections, utility work or construction.
If the agency finds the application incomplete or issues corrections, the time the applicant's team spends revising drawings and resubmitting is outside the agency's clock. Complete, coordinated drawings are the part of the schedule the owner's team controls most.
Water, sewer, electric and gas connections are reviewed and scheduled by the utility or agency that owns each system, sometimes on separate applications. Their timing is not set by the ADU review clock; ask each provider what it needs and when.
Once a permit is issued, duration depends on scope, site conditions, material lead times, inspections and any correction notices in the field. No general duration applies to every property; a schedule should be built from the actual scope.
Yes. California requires a local agency to approve or deny a complete ADU permit application within 60 days (Gov. Code §66317). The clock starts only when the application is complete; correction rounds, utility work and inspections are outside it.
Can monthly permit counts predict my approval time?
No. Census and city reports record authorizations issued, not how long each took. RSA shows those counts for context and asks you to enter your own week estimates per stage, labelled as your scenario.
It can affect concrete pours, roofing and excavation. The planning timeline flags days with rain chance of 40%+, wind of 20 mph+ or heat of 90°F+ as questions to ask your builder — not as a guaranteed work window.
241How long can a siding project take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
242How should a West Hollywood siding project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
243How long can a deck project take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
244How should a West Hollywood deck project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
245How long can a concrete project take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
246How should a West Hollywood concrete project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
247How long can a window and door project take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
248How should a West Hollywood window and door project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
249How long can a foundation work take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
250How should a West Hollywood foundation work schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
251How long can a framing scope take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
252How should a West Hollywood framing scope schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
253How long can a seismic retrofit take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
254How should a West Hollywood seismic retrofit schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
255How long can a hillside project take in West Hollywood?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
256How should a West Hollywood hillside project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
257How long can a ADU take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
258How should a Compton ADU schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
259How long can a garage conversion take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
260How should a Compton garage conversion schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
261How long can a JADU take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
262How should a Compton JADU schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
263How long can a home addition take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
264How should a Compton home addition schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
265How long can a kitchen remodel take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
266How should a Compton kitchen remodel schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
267How long can a bathroom remodel take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
268How should a Compton bathroom remodel schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
269How long can a whole-home remodel take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
270How should a Compton whole-home remodel schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
271How long can a roofing project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
272How should a Compton roofing project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
273How long can a siding project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
274How should a Compton siding project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
275How long can a deck project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
276How should a Compton deck project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
277How long can a concrete project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
278How should a Compton concrete project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
279How long can a window and door project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
280How should a Compton window and door project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
281How long can a foundation work take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
282How should a Compton foundation work schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
283How long can a framing scope take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
284How should a Compton framing scope schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
285How long can a seismic retrofit take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
286How should a Compton seismic retrofit schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
287How long can a hillside project take in Compton?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
288How should a Compton hillside project schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
289How long can a ADU take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
290How should a El Segundo ADU schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
291How long can a garage conversion take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
292How should a El Segundo garage conversion schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
293How long can a JADU take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
294How should a El Segundo JADU schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
295How long can a home addition take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
296How should a El Segundo home addition schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
297How long can a kitchen remodel take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
298How should a El Segundo kitchen remodel schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
299How long can a bathroom remodel take in El Segundo?+
There is no responsible citywide duration. Design decisions, consultant coordination, agency review, procurement, site conditions and construction scope all affect timing.
300How should a El Segundo bathroom remodel schedule be planned?+
Build the schedule around documented milestones, agency dependencies, owner decisions and material lead times, then update it as project information becomes more certain.
City timeline guides — the deep dive
Every FAQ above is anchored in real jurisdiction data. For full line-item breakdowns, plan-check timelines, and city-specific schedules, open the timeline guide for the city you're building in.