LADBS, ePlanLA, and the timeline you actually get

Permits in LA

How City of Los Angeles ADU plan check works — authority, submission, written corrections, clearances, and what the Standard Plan track does not replace.

Authority
Confirm first
postal city is not enough
Standard Plan
Design review
not a site-specific permit
Corrections
Written record
track comment, sheet, response
Statutory decision
Conditional
completed applications only

Permitting is the most opaque stage of an LA ADU. State law (Government Code §§ 66310–66342) makes ADU approvals ministerial — meaning no discretionary review — but local execution at LADBS still moves at LADBS pace. Here's how to read the system.

02.01The submission path

Plans are filed digitally through LADBS ePlanLA under the correct ADU pathway: new detached, attached, conversion, or Junior ADU. Each pathway has different setback, parking, and owner-occupancy rules under LAMC §12.22 A.33.

02.02Track property-specific clearances

Use the active agency record to identify assigned utility, fire, grading, planning or public-works review. Do not assume every property receives the same referrals or add a fixed duration without a written project record.

02.03When the Standard Plan track applies

A current LADBS Standard Plan can reduce repeat design review when the application and property qualify. It does not waive the building permit, zoning, foundation or site-adaptation review. Check catalog status and site conditions before selecting a plan.

From the desk

  • Reading an LADBS correction sheet without panicking

    Most corrections are clarifications. Here's how to triage them.

    5 min
  • Should I use a preapproved ADU plan?

    Compare plan rights, site work and current local programs without assuming a permit guarantee.

    10 min
  • Why the 60-day statutory clock rarely holds

    What the law says vs. what LADBS actually delivers.

    4 min